Today the Premier announced some clarifications to the restrictions that come into effect for our industry at 11:59pm Friday 7 August. Members are encouraged to read these guidelines and begin preparations for their implementation immediately. While many questions remain, this provides answers to some of the more important questions, as listed below:
- Movement among sites on small-scale residential sites: supervisors can move among sites and specialist trades can move among up to three sites per week, with no more than one site per day. This is subject to enhanced COVIDSafe practices.
- Small-scale residential sites will need to reduce the number of workers on-site to five workers plus a supervisor at any one time.
- During Stage 4 restrictions, large, commercial construction projects are allowed to have a maximum of 25 per cent of their workforce on site. All personnel count towards the 25 per cent with the exception of staff specifically dedicated to oversight of COVIDSafe functions in the workplace. Baseline workforce is the average daily number of personnel on site across the project life cycle, as derived from the project’s written resourcing plan as of July 2020. The resourcing plan and calculation are subject to audit.
- The definition of large-scale construction is as follows:
- More than three storeys (excluding basement), or
- Larger than 1,500m2 or
- Any office or retail fit-out, or
- Industrial, large format or retail use
We have sought clarification over whether the 25 per cent calculation will be subject to a minimum floor of five workers plus a supervisor
We have also sought urgent clarification from the government on the process for seeking exemptions for critical infrastructure and services. Further updates will follow on this and other outstanding items as soon as information becomes available.
Manufacturing of building and construction material will be allowed to continue.
Please read the full updated construction sector guidance on the Business Victoria website. Many of your specific questions will be answered within. We will continue to work on those areas where clarity is still needed and update you via bulletins and social media.
You'll also find links to useful documents that supplement the information provided in recent days, below:
- Permitted Work Premises– provides an update on the list of permitted workplaces
- Latest industry guidelines
- Yesterday’s COVID-19 special bulletin – provides details of the permit scheme and COVIDSafe Plans
- B6 - Workplace Directions – 5 August 2020 – provides further details of the general requirements for workplaces
- B7 – Permitted Worker and Childcare Permit Scheme Directions – 5 August 2020 – provides greater detail on the Permitted Worker rules.